| Outstanding
Environmental Project - Silver
Green Ridge Glade Reservoir Dam Expansion
Submitted by SEMA Construction
Inc.
The City of Loveland's Water Storage Dam Project involved
raising the existing Green Ridge Glade Reservoir Dam to increase
the city's storage capacity from 600 acre ft to more than
6,000 acre ft.
The project included nearly two million cu yds of engineered
dam and roadway embankment fill generated from onsite borrowed
sources; 26,000 ln ft of raw water supply line ranging from
18 to 54 in. in diameter; 8,000 cu yds of concrete backfill
and structures; and 60,000 yds of structural rock blasting.
From a constructability standpoint, this project presented
two unique challenges - water supply and fill placement. Before
construction could begin, the existing water supply facility
had to be taken offline.
SEMA Construction designed and installed an alternate supply
system capable of delivering 45 cu ft per second of raw water
from the city's supply gates located over one mi. from the
water treatment plant. SEMA increased the size and adjusted
the layout of planned future pipeline improvements to construct
a temporary gravity flow system that worked so well the city
elected to utilize it as a permanent alternate supply.
To meet an aggressive construction schedule and allow for
the capture of runoff one season ahead of schedule, SEMA placed
the majority of the fill during the winter of 2003-2004. SEMA
developed a method of rapid material placement coupled with
dry lifting and conditioning, resulting in fill material being
placed, compacted and covered before it could be adversely
impacted by winter conditions. This process also effectively
met the exacting standards for dam construction imposed by
the engineer, URS Corp. and the state engineer.
The innovative approach to the work, along with the cooperative,
common-sense mentality of the entire team, resulted in a quality
project completed under challenging circumstances within budget
and ahead of schedule.
Project Team
Owner: City of Loveland
Engineer: URS Corp.
General Contractor: SEMA
Construction Inc.
Major Subs: American Mine
Services, Layne Geo-Construction, Coulson Excavating
See
This Years Winners >>
|