Features
 Current Features
 Past Features





Cover Story - October 2007
 

The 2007 Colorado Construction Gold Hard Awards

Outstanding Public Projects

Gold Hard Hat Award

  • Memorial Hospital North
  • Submitted by: JE Dunn Construction

    To meet the health care needs of a growing community, Memorial Health System of Colorado Springs set out to construct a new hospital campus. As the first new hospital to be built in the community in 30 years, Memorial Hospital North brings the latest in health care design and technology to northern Colorado Springs.

    The project team set out to create a warm atmosphere that not only focused on meeting the patient’s medical needs, but also on providing total patient comfort. Located on an 82-acre site at Briargate Parkway and Union Boulevard, the first of three hospital buildings was designed with three elliptical-shaped wings.

    The 224,000-sq-ft, 89-bed hospital features entire columns constructed of glass at the end of each wing and a two-story atrium that fills the building with natural light. The private rooms, serene gardens and family areas contribute to a healing environment for patients and visitors.

    The unique design of the building required custom column forms to accommodate the elliptical wings while the concrete placement schedule was sequenced with 27 pours, totaling 8,452 yd of concrete completed within six months an accelerated project schedule.

    With a combination of soothing surroundings and the latest in medical advancements, Memorial Hospital North offers state-of-the-art medical technology in a patient-centered environment.

    Memorial Hospital North
    Colorado Springs

    PROJECT TEAM
    Owner: Memorial Health System
    Architect: Jonathan Bailey Associates
    Design Team:

    Bollar Cruz Architects, Cator, Ruma & Associates, Classic Consulting Engineers & Surveyors, CTL/Thompson, Gallun Snow, Martin/Martin, NES Inc.

    Contractor: JE Dunn Construction
    Among the Subcontractors:

    AAA Waterproofing, Acme Fire and Safety Equipment Co., Ambassador Steel, B & C Steel, Baker Concrete, Banner Rebar, Berwick Electric, Central States, Colorado Doorways, Concrete Coring, Concrete Frame Associates, Denver Drywall, Glover Masonry, Heating & Plumbing Eng., ISEC, Kenny Electric, LaFarge, Metropolitan Glass, Restoration Specialists, S&W Painting and Decorating, United Floor Co.

    Silver Hard Hat Award

  • Commerce City Civic Center
    Submitted by: RNL Design

    Commerce City’s new civic center is a state-of-the-art, energy-efficient home for the city’s government operations, justice center and police department. Located just south of the Prairie Gateway open space, the building also serves as an entryway to the Rocky Mountain Arsenal National Wildlife Refuge, which also influenced the project’s design.

    The building design emphasizes the importance of civic and environmental responsibility, energy efficiency and the beauty found in both natural and urban environments.

    The exterior design weaves together a natural and urban palette with the use of manufactured stone and a zinc metal wall panels. Both materials were selected for their beauty, longevity and ease of maintenance. The cool, white roof reduces the demand on the building’s cooling system and lessens the “heat-island effect.”

    The project is projected to save 40% on water through the use of ultra-low-flow plumbing fixtures and landscaping alternatives such as a native, drought-tolerant prairie grass seed mix for the large open areas, accented with other native drought-tolerant species.

    Most of the center’s 90,000 sq ft uses access-floor and under-floor air distribution, which enhances energy efficiency, occupant comfort and indoor air quality. Low-emitting materials were used throughout the interior, also enhancing environmental quality. The project is pursuing LEED silver certification.

    Commerce City Civic Center
    Commerce City

    PROJECT TEAM
    Owner: City of Commerce City
    Architect: S.A. Miro, Lund Partnership Inc., RNL
    Engineer:

    Martin/Martin Inc.

    Contractor: M.A. Mortenson
    Among the Subcontractors:

    Heating & Plumbing Engineers Inc., Duro Electric Inc., El Paso Glass -Denver Inc., Freelance Enterprises, EIG Group, Four Star Drywall, Western States Fire Protection

    Bronze Hard Hat Award (tie)

  • Aspen/Pitkin County Airport
    Submitted by: Kiewit Western

    Located at 7,815 ft above sea level, Aspen Airport’s single, dilapidated runway was in need of renovation. With only a 60-day airport closure period and no extra days allowed for inclement weather, the $12.7-million project called for intense management of schedule and resources.

    Kiewit’s scope of work included:
     • Milling and paving a 7,100-ft asphalt runway, taxiways and shoulders;
     • Replacing deep drainage pipe;
     • Paving the concrete and asphalt terminal areas;
     • Installing future runway sensor system conduit;
     • Constructing an airport-perimeter service road;
     • Setting pavement markings, seeding, lighting and signage.

    Before the winter shutdown, crews stockpiled asphalt aggregates, made drainage improvements, screened topsoil and completed electrical line work.

    When the airport closed on April 9, Kiewit had 125 employees, a temporary asphalt plant and 87 pieces of equipment onsite. Monitoring the scheduling milestones was critical, especially with liquidated damages of $12,500 per day and a construction pace totaling $300,000 per day.

    While the airport’s original plan allowed three taxiways to be closed until Aug. 1, Kiewit incorporated the work into the June 7 opening milestone to minimize impacts. Kiewit worked 24/7, logging more than 50,000 manhours without a recordable incident. Major quantities included 45,000 tons of asphalt, 3,800 ln ft of drainage pipe, 60,000 cu yd of excavation, and 25,000 cu yd of top soil.

    Aspen/Pitkin County Airport
    Aspen

    PROJECT TEAM
    Owner: County Commissioners, Pitkin County
    Engineer:

    Carter & Burgess

    Contractor:

    Kiewit Western Co.

    Among the Subcontractors: ACME Electric, Arapahoe Utilities & Infrastructure, Cardinal/International Grooving & Grinding LLC, Coatings Inc., Ideal Fencing Corp., Kolbe Striping, Urban Farmer Weed Wranglers Inc., Western Colorado Testing

    Bronze Hard Hat Award (tie)

  • Falcon High School
    Submitted by: GE Johnson Construction Co.

    The new Falcon High School in Colorado Springs is a $32-million, 176,000-sq-ft precast, masonry and steel structure that includes a finished auditorium, auxiliary gymnasium and a two-story classroom wing. The school is located on 70 acres, which consists of new baseball, softball, soccer, football fields, a running track, four tennis courts, student and staff parking lots, bus parking with an access road, as well as a water retention pond. Work began on the school in May 2006 and finished in September 2007.

    The school is designed to accommodate 1,200 students (grades 9-12) at full capacity. The design encompasses a future two-story classroom wing expansion, future portable classrooms, two tennis courts and additional soccer fields.

    The project team collaborated on the auditorium’s mechanical, electrical and fire protection systems using a three-dimensional computer model of the space and inserting 3D-systems models from subcontractors into the virtual environment. As a result of the process, nearly every duct in the auditorium had to be redesigned to coordinate with the steel truss structure. The fire protection system also required numerous revisions to accommodate the revised mechanical ductwork.

    This project was designed for LEED-Silver certification, including the use of sunshade canopies along the exterior portion of the walls, interior light shelves to reflect direct sunlight and tubular skylights.

    Falcon High School
    Colorado Springs

    PROJECT TEAM
    Owner: Falcon School District #49
    Architect:

    LKA Partners Inc.

    Engineers:

    HCDA Engineering Inc., CEI Inc., Systems Engineering Inc., Terra Nova Engineering Inc.

    Contractor: GE Johnson Construction Co
    Among the Subcontractors:

    Cobb Mechanical, Stresscon, Midwest Steel, LPR Construction, West Electric, Denver Drywall, El Paso Floor

     

    Click here for more Features >>



  •  


    Sponsors

    © 2009 The McGraw-Hill Companies, Inc.
    All Rights Reserved