|
2,000 More Spaces
Denver International Airport adding a new parking garage on the west side
The new west-side parking module will add about 2,000 spaces to the 38,000-plus parking spaces already at DIA.
By Chryss Cada
Improvements at Denver International Airport will create
more places to park, but they won't offer any help in actually
finding your car.
A fourth module of the parking garage being added on the west
side of DIA's Jeppesen Terminal will look identical to the
existing modules but will include structural changes not visible
from the exterior.
"Mod 4 has a new and improved design that will help to
save on maintenance costs," said John Luthi, general
superintendent for Denver's FCI Constructors Inc., the general
contractor on the new parking structure. "They had movement
they didn't anticipate in the other garages, so changes were
made to avoid that movement in this structure."
High Security
The new module will add about 2,000 spaces to the 38,000-plus
parking spaces at DIA - but don't expect to pull into the
new garage until next holiday season. Construction on the
$41.9 million, 18-month project began this summer and isn't
expected to be completed until late 2007.
"Right now we're doing roadwork more than anything,"
Luthi said. "We're having to shift a road that ran right
through the footprint of the garage."
Preconstruction started in June, with FCI opening up an office
on the site in July.
Denver's Harold Massop & Associates is the architect on
the project.
Since the project is on airport property, strict security
requirements must be followed on the jobsite.
"There's a lot of coordination involved in working with
every entity to make sure everyone has the proper badging
to start work," Luthi said.
The job was under way as of late September, with the hole
dug and work on the retaining walls started. When completed,
Mod 4 will connect with the terminal via a pedestrian bridge.
As construction of a new module begins, DIA's other garages
are having some work done. Phase II of the airport parking
structure's moisture-protection project is under way in Mod
1.
"The project is a combination of repair work and preventative
measures," explained Michael Steffens, assistant deputy
manger of maintenance and engineering/construction at DIA.
"We're replacing sections where moisture has gotten into
the concrete and is rusting the rebar. In addition, we'll
apply caulking sealant to prevent further damage."
John Rohre Contracting is the general contractor on the $6.1
million Mod 1 project.
Kirt Courkamp, branch manager of the Denver office, said the
project will include both full-depth and partial-depth structural
concrete work - and an "awful lot of sealant."
"I've worked on a lot of parking garages, and this type
of damage isn't uncommon in our climate," he said. "It
would fall under the category of routine maintenance.
This is something that needs to be done every five to 10 years."
Rohre contracting completed Phase I of the project, which
consisted of similar work on the top floor of DIA's parking
garages.
Steffens said that the contractors start at the top and work
their way down. "We close three floors at a time, averaging
400 to 900 parking spots closed at any given time," he
said.
A 3500-space expansion of the Pikes Peak parking lot was opened
in November 2005 to offset parking losses during construction
on the existing garages.
The moisture-protection project began this summer and is expected
to be completed by late summer 2008.
Runway Work
Also in the routine maintenance category, DIA is rehabilitating
sections of its runway system.
"Runway maintenance is an ongoing thing because there
is a very high level of standards for airfield concrete,"
Steffans said. "You can't have a chuckhole on a runway
or you could cause serious damage to an airplane. It doesn't
take much to shut a runway down."
A pothole three in. deep with sides at a 45 degree angle is
enough to close a runway to air traffic. To avoid such closures,
airport maintenance monitors the airfield "every day,
several times a day" and regularly replaces concrete
panels, Steffans said.
Nineteen concrete panels were replaced on Runway 7/25 and
about a dozen on Taxiways B4 and F this spring. In August
and September, 34 concrete panels were replaced on Runway
16L and 34R. The final phase of the project will replace 92
panels on Taxiway CN by early November. The project will cost
an estimated $10.6 million.
In addition to a smooth trip down the runway, visitors to
DIA will enjoy two new gates on Concourse C, thanks to a recently
completed construction project. The Concourse C west apron
expansion project added Gates C28 and 29, which were operational
by the end of August. The gates service passengers on US Air
and America West Airlines. Plane-loading bridges and exterior
pavement work were a part of the $5.7 million project, which
began last summer.
"It was one of those projects where everything comes
together and it goes very quickly," Steffans said. Interstate
Highway Construction was the general contractor on the project.
Stay tuned for future projects out at the state's largest
airport. "We make a plan for capital improvements every
year," Steffans said. "It's a six year program because
in this business, you really have to plan ahead."
Click here for
more Features >>
|