|
Project of the Year Honored for Community-Friendly
Approach
TSP Inc. Scott Broadway Street Reconstruction project was
selected as the Colorado/Wyoming American Concrete Pavement
Association Project of the Year in the category of Municipal
Streets under 30,000 sq yds.
The Scott Broadway reconstruction project was 12 blocks of
complete street reconstruction, including utilities, street,
sidewalk and all features within the existing right-of-way.
Streetscape enhancements such as colored sidewalks, traffic
calming bump-outs and decorative lighting were incorporated
in the project. The total project cost was $4.7 million, subsidized
by state funds, local tax dollars, and grants. The project
began March 10, 2005 and was completed October 10, 2005.
The project started at the front door of the historic Sheridan
Inn, which is on the national register of historic buildings.
The impact on the building was a major concern for the owner.
The following is a quote TSP received in a letter after the
project was completed:
"I wanted you to know how much I appreciated the concerns
of your staff regarding the needs of the historic Sheridan
Inn during the project. [Project Manager] Randy Bomar was
outstanding and a great pleasure to work with. I thought the
Scott Broadway construction project was one of the smoothest
that I have ever been involved with. I have no doubt that
TSP's leadership role played a huge part in that success.
Thanks again for a wonderful project," said Edre Maier
of the Sheridan Heritage Center.
Innovation
The State Historic Preservation Office required bricks, or
a brick pattern, in place of the historic cobblestones that
were removed. In Sheridan, colored concrete is usually placed
as an integral color and then stamped. A unique technique
was introduced called the Spray-rite© application process.
The City of Sheridan and the nearby business owners liked
the results.
Challenges
The project encountered some challenges. Planning and coordination
between the contractor, S&S Builders LLC, and TSP Engineers
was the key to completing the work while maintaining residential
and business access. The project was constructed in three
phases, and each phase needed to be substantially complete
before the next one could begin.
The contractor could not close more than two consecutive
intersections at any one time in order to maintain access
for residents and businesses. In addition, the complexity
of having four track hoes, loaders, haul trucks, pickups,
rollers and workers all restricted to working within a two-block
business district created a highly congested work environment.
The project took place in a part of town where the utilities
are over 50 years old. During excavation, three underground
fuel tanks were discovered that required decommissioning and
disposal, as well as removal of the contaminated soils surrounding
them. To address environmental concerns associated with the
contaminated soil plumes, pipe materials had to be quickly
revised to protect the public water supply.
During construction, a 50-year rainfall occurred, lasting
for three days and causing major flooding that seriously damaged
utility trenches, subgrades and exposed aggregates. Despite
the challenges that occurred throughout the project, it was
completed 30 days ahead of schedule.
Randy Bomar, principal; and Chad Lynn, EIT; attended the
CO/WY ACPA workshop in Greeley in early February. TSP sponsored
a booth and during the event, TSP was presented with a plaque
for the award.
ACPA Awards
Annual Concrete Pavement Awards in Colorado and Wyoming for
Projects Constructed in 2005
Urban Divided
Highways
I-70, Exit 114 Improvements
Glenwood Springs
Owner:
Colorado Department of Transportation, Region 3
Designer:
Felsburg, Holt and Ullevig
Contractor: Becvarik Brothers
Concrete Inc. and KECI Colorado Inc.
Municipal Streets and Intersections, Under
30,000 sq yds
Scott Broadway Reconstruction
Sheridan, Wyo.
Owner: City of Sheridan,
Wyoming
Designer: TSP Inc.
Contractor: S & S
Builders LLC
Municipal Streets
and Intersections, Over 30,000 sq yds
Grand Avenue Paving Project
Glenwood Springs
Owner: Colorado Department
of Transportation, Region 3
Designer: Colorado Department
of Transportation, Region 3, Glenwood Springs Residency
Contractor: Concrete Works
of Colorado Inc.
State Roads Project
U.S. 287
South of Laramie, Wyo.
Owner: Wyoming Department
of Transportation
Designer: Wyoming Department
of Transportation, District 1, Laramie Residency
Contractor: Interstate
Highway Construction Inc.
Commercial Service
& Military Airport Project
Taxiway H Reconstruction
Colorado Springs Airport
Owner: City of Colorado
Springs, Department of Aviation
Designer: URS Corp.
Contractor: Interstate
Highway Construction Inc.
General Aviation Airport and Overlay Projects
Rehabilitate and Expand Commercial Apron
Rock Springs, Wyo.
Owner: Rock Springs -
Sweet Water County Airport
Designer: Airport Development
Group Inc.
Contractor: Concrete Works
of Colorado Inc.
Concrete Pavement Restoration Project
I-70, Rifle to Silt, Diamond Grind
Owner: Colorado Department
of Transportation, Region 3
Designer: Colorado Department
of Transportation, Region 3, Glenwood Springs Residency
Contractor: American
Civil Constructors
Urban Arterials & Collectors Project
and Traffic Management Project
Wyoming Boulevard Reconstruction
Yellowstone Highway to 15th Street, Casper, Wyo.
Owner: Wyoming Department
of Transportation
Designer: Wyoming Department
of Transportation, District 3, Casper Residency
Contractor: Interstate
Highway Construction Inc.
2005 ACPA Colorado/Wyoming Chapter Workshop
CDOT Highway Commissioner Bill Kauffman opened the 23rd Annual
Concrete Pavement Workshop in Greeley in February. As the
keynote speaker, Kauffman told the 400 attendees about the
state's plans to fund more transportation projects. In 2006,
he said this means rebuilding and expanding some of the oldest
highways in the system, including some 40-year-old pavements
that have never been overlaid.
Many of the other projects have been overlaid several times
in the last 20 years. They were never designed for the traffic
and rapid growth that Colorado has experienced in the last
decade. Concrete pavement will solve those problems. The reconstruction
of those projects with concrete, like I-25 from S.H. 52 to
S.H. 119, will reduce CDOT's future maintenance costs.
People who missed this year's ACPA workshop missed several
informative sessions and demonstrations, some of which are
pictured here.
Click here for
more Features >>
|