|
Road Work Ahead
COSMIX crews will shift into overdrive this
summer as major reconstruction of I-25 begins
COSMIX - The $150 million Colorado
Springs Metro Interstate Expansion - will widen Interstate
25 through Colorado Springs, helping ease congestion along
a stretch of highway that has seen a dramatic increase in
traffic in the last five decades.
 |
| Photo by Jackie Shumaker |
The largest highway project in the history of Colorado Springs
will hit the one-year mark this summer, ushering in a period
of the most intense construction yet.
The $150 million Colorado Springs Metro Interstate Expansion
- best known as COSMIX - will widen I-25 to three lanes in
each direction from Circle Drive to North Academy Boulevard
and improve the configuration of several key interchanges
and bridges along the 12-plus miles of the corridor.
Ground was broken in early July 2005. Although the original
plan asked for a 2008 finish, Rockrimmon Constructors, a joint
venture between CH2M Hill and SEMA Construction Inc., committed
to completing the job in 2007 - a promise upon which the contractor
might even improve.
"We're actually advancing the schedule," said Rockrimmon's
Bill Badger. "We've realized now that [finishing in 2007]
is more than reachable, and so we're reaching to get it done
even earlier."
Easing Congestion
COSMIX was born from the undisputed need to widen Interstate
25 through Colorado Springs, a stretch of highway that, like
so many other areas of the Front Range, has seen a dramatic
increase in traffic in the last several decades.
"When this stretch of I-25 opened in 1960, the highway
carried about 8,500 vehicles a day," Gov. Bill Owens
said during the July 5 groundbreaking ceremony. "Now,
45 years later, some 100,000 vehicles travel I-25 every day
through Colorado Springs. And by 2020, that number is projected
to be 170,000 vehicles per day."
Colorado Department of Transportation Executive Director
Tom Norton agreed.
"COSMIX is the next step for highway transportation
in Colorado Springs," said Norton. "This project
will be a significant step in reducing congestion through
this busy corridor."
The project is part of CDOT's long-term plans to ease congestion
and improve mobility on I-25 through the Pikes Peak region.
It's being funded by a TRANs bond ballot initiative approved
by voters in 1999.
"CDOT committed to completing the six-laning of I-25
through Colorado Springs by 2007 and COSMIX meets that commitment,"
Norton said. "Without funding from the TRANs bond program,
this project would not be completed until 2018 at the soonest."
The city of Colorado Springs and Pikes Peak Rural Transportation
Authority also committed $10 million, enabling the extension
of North Nevada Avenue to Corporate Center Drive, as well
as the reconstruction of the Bijou Street Bridge over Monument
Creek.
People-Pleasing Plan
The overall plan for completing COSMIX follows this general
timeframe:
- Summer 2005 through end of the year - Construction of
I-25 south of Mark Dabling, from Garden of the Gods Road
to Fillmore Street.
- Fall 2005 through Fall 2006 - Construction of the Nevada
and Rockrimmon ramps, a new southbound frontage road and
the Corporate Drive extension.
- Spring 2006 through Fall 2006 - Widening I-25 mainline
between Woodmen Road and North Academy Boulevard.
- Summer 2006 through Fall 2007 - Reconstruction of the
Bijou interchange, including replacement of the Bijou bridge
(which will be closed from January 2007 through October
2007) and completion of the newly reconfigured Rockrimmon
Boulevard/Nevada interchange.
- Summer 2006 through Winter 2007 - Work on I-25 mainline
and completion of the reconfigured Rockrimmon Boulevard/Nevada
interchange.
The work completed to date has gone smoothly, even winning
raves from Colorado Springs residents who were polled last
December about the project.
More than 60 percent of Colorado Springs residents who live
along Interstate 25 said COSMIX is progressing well or extremely
well; 55 percent of commuters and 80 percent of businesses
along I-25 also think everything is going well.
"The project team conducted the research as part of
the project's goal to minimize inconvenience to the public,"
said Dave Poling, CDOT's COSMIX project manager. "Construction
impacts are unavoidable, but we can minimize those impacts
to residents, businesses and commuters by effectively communicating
with them and explaining how construction activities impact
their daily lives so they can better cope with construction.
Knowing how they feel about the project and the effectiveness
of our communications efforts is key to this."
Badger believes people were primed to expect the worst once
construction began.
"I think people were expecting major traffic impacts,"
he said. "I think we're doing a pretty good job minimizing
the impacts and at least communicating to the public."
That said, big changes are just ahead.
"The big traffic shifts will be in June and July. That's
when we shift all I-25 traffic off the main line onto the
frontage roads we're building," Badger said. "That
opens up the entire interstate segment for reconstruction."
Work will also begin this summer on the Colorado Avenue bridge,
one of 20 bridges associated with COSMIX. The biggest impact
to commuters is expected to begin on Jan. 2, 2007, when crews
tackle the heavily trafficked Bijou Bridge.
"That's their lifeline to downtown," Badger said.
Design-Build Approach
COSMIX is using a design-build approach to provide the best
value for CDOT and a faster build-out of the project to reduce
inconvenience to the public. The traditional design-bid-build
method was not used because of the project's size and location
in a major urban area.
"One of the benefits of design-build is that it allows
for more flexibility," Badger said. "It allows us
to start construction in certain areas while other areas are
still under design."
Approximately 30 percent of COSMIX was designed before the
contract was awarded.
"You're starting construction earlier so you can address
problems earlier," Badger said.
Of course, the design-build approach comes with its own concerns.
"You do have the challenge of getting approvals in a
rapid turnaround from all agencies - the city, CDOT, contractor,"
Badger said. "For instance, sometimes some of the agencies
are looking for more information than is available. You just
have to go with what you've got and keep going."
As such, coordination and cooperation are key.
"We - CDOT and us, the contractor - have offices together
and the city comes to every one of our task force meetings,
which are pretty much weekly," Badger said.
'Sweetening the Pot'
Besides its commitment to finish COSMIX in 2007, Rockrimmon
Constructors signed onto the project with another promise:
to complete five optional elements on CDOT's "wish list"
of work that it couldn't fit into the project's fixed budget.
Seven Additional Requested Elements, or AREs, were included
in the request for proposal that CDOT issued for COSMIX in
September 2004. Proposals from contractors for the project
were judged, in part, on how many of the seven AREs they committed
to doing. Rockrimmon Constructors committed to completing
five of them.
"The added value in I-25 improvements that the Pikes
Peak region receives from these AREs, at no additional cost
to the taxpayer, was one of the key factors for CDOT in selecting
Rockrimmon Constructors," Poling said.
The AREs included work that began last fall on the ramps
at the Garden of the Gods/Interstate 25 interchange, designed
to improve safety and capacity at one of Colorado Springs's
busiest interchanges; reconstruction of the Colorado Avenue
bridge; improvements to the Mark Dabling interchange; and
the build-out of all bridges and corridors so that, in the
future, they can accommodate four lanes of traffic and full
shoulders.
"Those additional things are kind of sweetening the
pot," Badger said.
Seeing Green
The COSMIX project team has also kept an eye on the environment
throughout construction.
Last year, after completing work around the North Nevada
Avenue and Rockrimmon Boulevard interchanges, crews planted
more than 200 new trees native to Colorado. They were planted
along Monument Creek near I-25 to preserve the natural environment
and replace trees that will be lost during construction.
"Environmental conservation is an important facet of
the COSMIX project," Poling said. "With Monument
Creek running parallel to I-25 for virtually the length of
the project, our goal is to protect the scenic beauty and
ecology of the creek and ensure that the trail remains open
and enjoyable for recreational users."
Top
Biggest Heavy/Highway Contractors List >>
Click here for
more Features >>
|